Key point
Treat inverter replacement as a recommissioning task. Preserve a model-labelled baseline, verify any configuration transfer is supported, and obtain a final settings record and functional checks from an authorised installer.
Product ranges to review for this topic: Solis Three-Phase String Inverter · GoodWe Commercial & Industrial Inverter
Related product references: Solis S6-GC110K — String inverter · GOODWE GW100K-GT — String inverter
Save the baseline while the system works
Ask the installer for a dated configuration record and, where supported, a manufacturer-approved export. Label it with the device model, firmware and site. Keep an owner-controlled copy. Screenshots can help, but do not assume an export includes passwords or every installation setting.
Do not copy settings blindly
Have an authorised installer confirm whether the old file is suitable for the replacement model and firmware. Review applicable grid settings, export limits, metering and battery-related requirements for the actual site. A successful import is not proof that every required setting has been transferred correctly.
Close the job with a new record
Agree the functional checks with the installer and retain the results, final configuration, replacement serial number and date. Confirm monitoring and any required battery or export-control functions are working. Avoid changing protected grid or safety parameters yourself; unresolved differences belong in the installer’s completion report.
Further reading: manuals.sma.de · manuals.sma.de
This article supports early project discussions. Final configuration depends on site conditions.